This submodule in Fracttal One allows you to analyze different types of resources derived from task planning, in terms of quantities, costs, and origin, whether from inventory, Inhouse Personnel, or services, which will be executed according to the periods established in prior planning. The details of these results are displayed in a parametric format over time periods such as days, weeks, or months.
1. Locate the Date Filter
- At the top right of the screen, you will find a drop-down menu labeled "Actual/Scheduled Date". This menu allows you to select and apply different date filters.
2. Select the Desired Date Filter
When clicking on the "Scheduled Date" menu, the following options will be available:
- Actual Scheduled Date: Displays resources based on the date they were scheduled for execution.
- Creation Date: Filters resources based on the date they were created in the system.
- Start Date: Shows resources based on the planned start date for execution.
- End Date: Displays resources based on the planned end date for execution.
3. Choose the Period (Day/Week/Month)
- Next to the "Scheduled Date" menu, there is another drop-down menu with the available period options: Day, Week, and Month. Select the desired option to further refine your filter.
Example: If you select "Scheduled Date" and "Week", the system will display the resources scheduled for the current week.
4. Set the Start and End Date
- To the right of the period menu, there is a calendar icon. Click on it to select the start and end date of the period you want to view.
5. Apply the Filters
- Once you have selected the filters and the desired period, the system will automatically apply the changes and display the corresponding resources.